Table of Contents | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
|
v1.4.3
Performance Summary
Added and Analysis Option to toggle where the prestress is applied (Allowable vs. Demand)
...
In the handling stages this Analysis Option will change the layout of the demand and allowable values
...
Piece Ticket
Misc. fixes to the piece ticket output
Main Window
Print All now asks what you would like to print
Program Options
A new option was added to specify what number format the program will use (periods or commas as decimal points) in the option “Number Format”
Bug Fixes 🐛
Issue where some countries would experience crashes due to mismatched windows cultures not be appropriately handled.
Countries where a comma may be used in lieu of a period for decimal points was causing crashes
v1.4.2
Bug Fixes 🐛
Piles with only rebar reinforcement had drawing issues in the production summary, reinforcement tab, and the piece ticket.
Piles with only rebar reinforcement would crashed the program when using the Detensioning tool in the piece ticket.
Piles with only rebar reinforcement would display NaN for the allowable in the handling stages.
Piles with only rebar reinforcement would not display the interaction diagram in the Analysis summary.
...